MacGregor Park Is Split In Two For Construction. Here's The Half Still Open This Fall.

October 22, 2026

"This park has been a connection point for the entire Third Ward," Ken Rogers, president of the Greater Third Ward Super Neighborhood, told the Houston Chronicle at the Oct. 1 groundbreaking. For the next two years, that connection point works in halves.

The $75 million renovation of MacGregor Park runs in two phases, and it's built so the park never closes all at once. The southern section went first. The northern section, with the pool and the fitness center, stays open until it's expected to close in fall 2027. By then, if the schedule holds, the rebuilt south side should be close to reopening. So if you use the park every week, the useful question is which half is open right now and what's on it.

What's behind the fence since Aug. 17

Houston Parks Board's MacGregor Park page lists what closed when Phase One started on Monday, Aug. 17, 2026:

  • The Homer Ford Tennis Center
  • Disc golf
  • The baseball field
  • The large playground across from the fitness center
  • Sections of MacGregor Park Trail
  • Sections of parking

The City of Houston's park projects notice gives the same list and the same Aug. 17 start date. The trail and parking closures cover sections only, so parts of the loop and parts of the lots are still in use. Houston Parks Board posts a closure map with a legend on the same page. Look at it before you plan a walking route, because the fence line decides where a familiar lap gets cut short.

Justin Schultz, the Parks Board's CEO, told the Chronicle that this phase is expected to take 12 to 16 months. It covers the tennis complex, the playground, the baseball field and public infrastructure work. Counting from the August closure, that puts the south side's expected return somewhere between late summer and the end of 2027.

The north half is the park through 2027

Phase Two covers the pool, a new pool house with a community room, and upgrades to the fitness center and the existing basketball pavilion. None of those are on the Phase One closure list. That's why the north side matters so much right now: it's the half you still have, and it's expected to stay open until fall 2027.

The MacGregor Park Fitness Center is at 5225 Calhoun. The city's Southeast community center listing shows fall and spring hours of 7 a.m. to 7 p.m., Monday through Friday. The city's separate fitness center page lists weekdays from 7 to 1 and 2 to 7, plus Saturday from 10 a.m. to 2 p.m., with Sundays closed. The two pages don't agree on Saturdays, so call the center at 713-747-8650 before you plan a weekend workout around it.

The pool is closed for now, like every city pool. The city says the 2026 season has ended, and its normal pool season runs from Memorial Day through Labor Day. With Phase Two expected to start in fall 2027, summer 2027 looks like the last season in the current MacGregor pool before the renovation reaches it.

How the two halves are expected to hand off

Phase One Phase Two
Area Southern section Northern section
Closed Since Aug. 17, 2026 Expected fall 2027
Work Tennis complex, playground, baseball field, trails, trees, infrastructure Pool and pool house, fitness center, basketball pavilion
Expected length 12 to 16 months Project done by late 2028

The Phase Two date comes from the Chronicle's reporting and is an expected date, not one the Parks Board has posted. Both phases could shift. As written, though, there's no planned stretch when the whole park is fenced off. Houston Parks Board's Oct. 1 announcement says portions of the park will stay open throughout construction, with completion expected in late 2028.

Where tennis and the playground moved in the meantime

The fenced-off half is the one that held the tennis courts and the big playground. Those are the hardest things to replace on short notice. Houston Parks Board lists these alternatives for the construction period:

Nearby parks: Fonde Park, Smither Park, the Gragg Park Complex, George T. Nelson (Yellowstone) Park and Emancipation Park.

Tennis courts: Memorial Park Tennis Center, Zollie Scales Park, Mason Park and Sunnyside Park.

If you have kids in tennis, the city's youth tennis page lists fall 2026 programs at Alief Park, Memorial Park Tennis Center, Lee LeClear Tennis Center and Pumpkin Park, with sessions running Sept. 1 to Nov. 20. The HPARD Tennis Dreamers fall program meets at Lee LeClear Tennis Center from Aug. 31 to Dec. 16. The city doesn't describe these as relocated MacGregor programs. They're simply the current fall sites.

Emancipation Park picks up some of the slack

Of the parks on the Parks Board's list, Emancipation Park, at 3018 Emancipation Ave., overlaps most with what's missing at MacGregor right now. The Emancipation Community Center keeps fall and spring hours of 9 a.m. to 8 p.m. on weekdays and 10 a.m. to 2 p.m. on Saturdays, and it's closed Sundays. The Emancipation Park Conservancy describes a recreation center with a gymnasium and activity room, and the park's facilities include a baseball field. That matters while MacGregor's field is behind the fence.

The next big date on the calendar is Saturday, Oct. 31. That morning, The Greening of Third Ward & Beyond runs from 9 a.m. to noon at 3018 Emancipation Avenue, with free plants, gardening demonstrations, local growers and family activities. The Emancipation Park Conservancy's event listing names Harlem River Farms as the organizer and files it under the Harlem River Farmers Market. Admission is free, and registration is encouraged. It falls on Halloween, so a family can do the morning at Emancipation and still be home for the evening.

What the south half brings back first

The fenced-off half also gets its work finished first. Houston Parks Board lists the Phase One improvements as:

  1. A new tennis complex with a clubhouse, 16 tennis courts, 2 practice courts and 8 pickleball courts
  2. An all-inclusive, heavily shaded playground
  3. More than 3,000 new trees
  4. Over three miles of new walking trails and sidewalks
  5. Expanded space around the MLK, Jr. and Tree of Life Plaza
  6. Better connections to the Brays Bayou Greenway

The tennis complex is the headline. Houston Parks Board notes that Olympic and professional athletes trained at the Homer Ford Tennis Center. The master plan calls for renovating the center into a state-of-the-art facility that can host tournaments, and that work sits in the half expected to reopen first.

The project has also grown. The Chronicle reports the cost rose from $57.5 million to $75 million after the plans were unveiled in March 2025. Funding includes a $27 million catalyst gift from Kinder Foundation, $6.5 million from the City of Houston, $4 million from TIRZ 7 and a $10 million federal Outdoor Recreation Legacy Partnership grant. Gifts from The Brown Foundation, Texas Children's Hospital, The Cullen Foundation and others cover the rest. Hood Design Studio created the concept. Talley Landscape Architects is the landscape architect of record, and Bellows Construction is building it.

Schedules for a project this size change. The Parks Board runs a mailing list for MacGregor Park updates, and that's where any change to the fence line or the Phase Two start should show up first.

When a park this central to a neighborhood is rebuilt over two years, it changes how the streets around it feel day to day, and a lot of that isn't on a closure map. If you live near MacGregor and want to talk through what the renovation timeline could mean for your block, Denise Moore Homes is happy to walk through it with you. Let's Connect.